The construction
Dredging
After the disaster, the building of the barrier was sped up. Preparations started less than a year later, on January 18, 1954. The barrier would be built on the Hollandse IJssel estuary in the Nieuwe Maas (New Maas), between Krimpen aan de IJssel and Capelle aan de IJssel. At this point, the river is only 250 metres wide. A lot had to happen before they could actually start constructing the barrier. Firstly, the hindrance on shipping traffic had to be kept as small as possible. On average, 250 ships passed through each day. By dredging a part of the forelands, ships were able to sail without being hindered, and at the same time, work on the river could continue. Secondly, various clay layers had to be removed, because they were too weak to build a barrier upon. The clay was dug up and replaced with sand. The suction ship ‘Ahoy’ sucked up the sand from the Nieuwe Maas near Vlaardingen. The sand was transported via ships to Capelle where it was discharged by two floating transport cranes. The Nieuwe Waterweg needed to be dredged anyway, so by replacing the clay with sand, they reached two goals.Dam walls
In July 1954, they finished the dredging operations and they started driving the steel dam walls. On the inside of the dam walls they were able to start pumping away the water. 100 kilometres of dam walls were used to build this excavation. A large majority of the work wasn't done above, but under the water. The dam works by lowering down 80 metre wide metal screens. However, without proper precautions, these screens would be too heavy to be supported by the riverbed.Thresholds
Therefore, a kind of threshold was built to carry the dam walls. A dry dock of 80 metres wide was needed, because the threshold had to have the same length as the screens. This appeared to be impossible, because a large part of the Hollandse IJssel would have to be closed for shipping traffic. Therefore, two enormous thresholds were built in parts. Every threshold consisted of two parts with a width of 27.5 metres each. These parts were placed in the middle of the river. Afterwards, by linking the parts together with two extra parts of 12.5 metres, a connection with the banks was made.
The thresholds were built with a special shape, because of the risk that the surrounding ground could be washed away. But unfortunately, due to this special shape, the stability of the thresholds was in danger. As the screens are lowered, the waterflow is increased because the area the water has to flow through is decreased. Immediately before the screens are completely down, the flow is at its fastest point. It is this high water flow that could wash away the ground.





